Project Status District 57 - Wilson - 3/19/2009


WILSON - SUMNER COUNTIES
SR-109 FROM SR-24 (US-70) TO SR-109 BYPASS SOUTH
OF GALLATIN
Length - 8.6 (Location and Environmental Study)
The environmental document is underway.

WILSON - SUMNER COUNTIES
SR-109BRIDGE OVER CUMBERLAND RIVER, LM 14.91
Length - 1.0 (Bridge Replacement)
The engineering is underway

WILSON - DEKALB COUNTY
SR 26 SR 70 Under Development in Wilson County
WEST OF WILSON COUNTY LINE TO NEAR SR-96 IN
DEKALB COUNTY
Length - 6.2 (Reconstruction)
The right-of-way and/or utility process is underway.

WILSON COUNTY I-40
INTERCHANGE AT SOUTH HARTMANN DRIVE IN LEBANON
Length - 0.0 (Interchange Lighting)
A contract for construction is scheduled to be let in the 2nd
Quarter Calendar Year 2009.

WILSON COUNTY SR-26 US-70
INTERSECTION AT MADDOX-SIMPSON PARKWAY IN
LEBANON
Length - 0.0 (Intersection Improvements)
The engineering is underway

WILSON - SUMNER COUNTIES SR-109
FROM SR-24 (US-70) TO SR-109 BYPASS SOUTH OF
GALLATIN
Length - 8.6 (Location and Environmental Study)
The environmental document is underway.

WILSON - SUMNER COUNTIES SR-109
BRIDGE OVER CUMBERLAND RIVER, LM 14.91
Length - 1.0 (Bridge Replacement)
The engineering is underway

WILSON COUNTY SR-141
NORTH OF LOVERS LANE TO STATE ROUTE 26 (US-70)
Length - 1.8 (Construction-New)
The engineering is underway

WILSON COUNTY SR-141
SOUTH OF SPRING CREEK TO NORTH OF LOVERS LANE
Length - 1.5 (Widen)
The engineering is underway

WILSON COUNTY SR-141
SOUTH OF SPRING CREEK TO THE TROUSDALE COUNTY
LINE
Length - 14.1 (Right-of-Way)
The right-of-way and/or utility process is underway.

WILSON COUNTY SR-141
NORTH OF TOMLISON ROAD TO TROUSDALE COUNTY LINE
Length - 3.9 (Reconstruction)
The preliminary engineering and right-of-way is being
accomplished on the project from South of
Spring Creek to the Trousdale County Line.

WILSON COUNTY SR-171
MOUNT JULIET ROAD; DIVISION STREET TO SR-24 (US-70,
LEBANON ROAD)
Length - 2.2 (Reconstruction)
A contract for construction is scheduled to be let in the 2nd
Quarter Calendar Year 2009.

WILSON COUNTY SR-171
INTERSECTION AT STEWARTS FERRY PIKE, LM 1.61
Length - 0.0 (Signalization)
The right-of-way and/or utility process is underway.

WILSON COUNTY SR-171
INTERSECTION AT WESTON DRIVE, LM 5.84 IN MT. JULIET
Length - 0.0 (Flashing School Sign)
This project is currently advertised for the March 20, 2009
contract letting.

WILSON COUNTY
OLD LEBANON DIRT ROAD, DAVIDSON COUNTY LINE TO
EAST OF ESSEX LANE IN MT.
JULIET
Length - 2.9 (Reconstruction)
The engineering is underway

WILSON COUNTY
LINWOOD ROAD, BRIDGE OVER I-40, LM 7.81
Length - 0.0 (Bridge Replacement)
The engineering is underway

WILSON COUNTY SIA
STATE INDUSTRIAL ACCESSS ROAD SERVING CORETECH
CORPORATE PARK, I-40 AND
FRANKLIN ROAD FROM APPROX. 1200 FEET WEST OF
SOUTH HARTMAN DRIVE AND
EXTENDING APPROX. 2100 FEET TO OLD SHANNON ROAD,
LEBANON, WILSON COUNTY.
(Other)
The engineering is scheduled to begin in the 1st Quarter
Calendar Year 2009.

WILSON COUNTY SR-109
SR-109, NEAR (DIVISION STREET) TO SOUTH OF SR-24
(US-70) (WIDEN) LENGTH - 2.938
CONTRACT NO.: CNG925
LET TO CONTRACT: 9/19/2008
CONTRACTOR: LOJAC ENTERPRISES, INC.
BID PRICE : $15,559,389.21
EST. COMPLETION DATE: JUNE, 2011

WILSON COUNTY SR-109
FROM I-40 TO NORTH OF NORTH FORK CEDAR CREEK
(CONSTRUCTION-NEW) LENGTH - 0.300
CONTRACT NO.: CNG925
LET TO CONTRACT: 9/19/2008
CONTRACTOR: LOJAC ENTERPRISES, INC.
BID PRICE : $2,992,786.70
EST. COMPLETION DATE: JUNE, 2011

WILSON COUNTY SR-141
SOUTH OF SPRING CREEK TO TOMLINSON ROAD
(RECONSTRUCTION)
CONTRACT NO.: CNG101
LET TO CONTRACT: 6/20/2008
CONTRACTOR: LOJAC ENTERPRISES, INC.
BID PRICE : $9,906,165.78
EST. COMPLETION DATE: OCTOBER, 2010

WILSON COUNTY
INDUSTRIAL ACCESS ROAD SERVING NASHVILLE WIRE
(WIDEN AND RESURFACING) LENGTH -
0.562
CONTRACT NO.: CNF032
LET TO CONTRACT: 4/27/2007
CONTRACTOR: CIVIL CONSTRUCTORS, INC.
BID PRICE : $2,124,520.85
EST. COMPLETION DATE: MARCH, 2009

WILSON COUNTY I-40
INTERCHANGE AT SR-171(MT JULIET ROAD)
(RECONSTRUCTION) LENGTH - 0.820
CONTRACT NO.: CNF007
LET TO CONTRACT: 2/2/2007
CONTRACTOR: ROGERS GROUP, INC.
BID PRICE : $10,851,867.18
EST. COMPLETION DATE: MARCH, 2009

Project Status District 57 - Sumner - 319/2009


SUMNER - DAVIDSON COUNTY
Project Under Development in Sumner County
(DICKERSON PIKE), BRIDGE OVER MANSKER CREEK
Length - 0.0 (Bridge Replacement)
The engineering is underway

SUMNER - DAVIDSON COUNTY
SR-11 US-31W (DICKERSON PIKE), INTERSECTION OF OLD
SPRINGFIELD HWY
Length - 0.1 (Intersection Improvements)
The engineering is underway.

ROBERTSON - SUMNER COUNTY I-65
PROPOSED INTERCHANGE, EXISTING SR-109 TO I-65
Length - 0.8 (Environmental Studies)
This project is in the early stages of development.

SUMNER COUNTY SR-6 US-31E
WEST EASTLAND AVENUE TO COLLEGE STREET IN
GALLATIN
Length - 0.0 (Realignment)
The right-of-way and/or utility process is underway.

SUMNER - ROBERTSON COUNTIES SR-41 US-31W
SOUTH OF SR-109 TO KENTUCKY STATE LINE
Length - 0.4 (Reconstruction)
The state of Kentucky is designing and building this project.

SUMNER COUNTY SR-109
NORTH OF THE CUMBERLAND RIVER BRIDGE TO SR-109
BYPASS SOUTH OF GALLATIN
Length - 1.3 (Widen)
The engineering is underway.

SUMNER COUNTY SR-109
SR-109(GALLATIN BY-PASS) TO HOLLIS CHAPEL ROAD
Length - 5.2 (Paving)
A contract for construction is scheduled to be let in the 2nd
Quarter Calendar Year 2009.

SUMNER COUNTY SR-109
SOUTH OF HOLLIS CHAPEL ROAD TO SOUTH OF SR-76
Length - 4.1 (Reconstruction)
The right-of-way and/or utility process is underway.

SUMNER COUNTY SR-109
INTERSECTION AT KIRBY DRIVE IN PORTLAND
Length - 0.0 (Intersection Improvements and Signals)
The engineering is underway

SUMNER COUNTY SR-386
INTERCHANGE AT FOREST RETREAT ROAD
Length - 0.0 (New Interchange)
The right-of-way and/or utility process is underway.

SUMNER COUNTY SR-386
DETENTION POND NEAR SHUTES LANE
(Miscellaneous Improvements)
This project is in the early stages of development.

SUMNER COUNTY
KEY TOWN ROAD, BRIDGE OVER WEST FORK DRAKES
CREEK, LM 3.35
Length - 0.0 (Bridge Replacement)
The engineering is underway

SUMNER COUNTY
ROCKLAND ROAD/IMPERIAL BLVD, CENTER POINT ROAD
TO IMPERIAL BOULEVARD IN
HENDERSONVILLE
Length - 1.3 (Reconstruction)
Locals are performing the engineering.

SUMNER COUNTY
WALTON FERRY ROAD/OLD SHACKLE ISLAND ROAD,
FROM IMPERIAL BOULEVARD TO
VOLUNTEER DRIVE IN HENDERSONVILLE (SECTION 1)
Length - 0.7 (Widen)
The engineering is underway

SUMNER COUNTY
CARTWRIGHT PARKWAY EXTENSION IN MILLERSVILLE
Length - 0.2 (Construction-New)
Locals are performing the engineering.

SUMNER COUNTY
ALBERT GALLATIN AVENUE / HATTENTRACK ROAD
EXTENSION, SR-109 TO SR-174
Length - 0.8 (Construction-New)
The planning document is underway.

SUMNER - WILSON COUNTIES SR-109
FROM SR-24 (US-70) TO SR-109 BYPASS SOUTH OF
GALLATIN
Length - 8.6 (Location and Environmental Study)
The environmental document is underway.

SUMNER - WILSON COUNTIES SR-109
BRIDGE OVER CUMBERLAND RIVER, LM 14.91
Length - 1.0 (Bridge Replacement)
The engineering is underway

SUMNER COUNTY SR-6
Under Construction in Sumner County
LOWER STATION CAMP CREEK ROAD TO LOCK 4 ROAD
(RESURFACING) LENGTH - 3.770
CONTRACT NO.: CNH026
LET TO CONTRACT: 2/6/2009
CONTRACTOR: ROGERS GROUP, INC.
BID PRICE : $1,225,405.90
EST. COMPLETION DATE: JUNE, 2009

SUMNER COUNTY SR-6 US-31E
(US-31E, NASHVILLE PIKE), INTERCHANGE AT SR-109
NORTHBOUND RAMP IN GALLATIN
(MODIFY INTERCHANGE)
CONTRACT NO.: CNG347
LET TO CONTRACT: 12/12/2008
CONTRACTOR: SESSIONS PAVING COMPANY
BID PRICE : $586,031.25
EST. COMPLETION DATE: AUGUST, 2009

SUMNER COUNTY SR-109
SOUTH OF SR-76 TO SR-52 IN PORTLAND
(RECONSTRUCTION) LENGTH - 2.300
CONTRACT NO.: CNG181
LET TO CONTRACT: 6/20/2008
CONTRACTOR: CBM ENTERPRISES, INC.
BID PRICE : $12,699,143.58
EST. COMPLETION DATE: OCTOBER, 2010

DAVIDSON - SUMNER - WILLIAMSON COUNTY
NASHVILLE ITS PHASE 3 AT VARIOUS LOCATIONS
(INTELLIGENT TRANSPORTATION SYSTEM)
LENGTH - 115.000
CONTRACT NO.: CNF075
LET TO CONTRACT: 10/19/2007
CONTRACTOR: TRANS TECH ELECTRIC, L.P.
BID PRICE : $41,146,448.95
EST. COMPLETION DATE: MAY, 2010

SUMNER COUNTY SR-109
SR-109 BY-PASS (GALLATIN BY-PASS) TO HOLLIS CHAPEL
ROAD (STAGE CONSTRUCTION-NEW)
LENGTH - 5.250
CONTRACT NO.: CND199
LET TO CONTRACT: 7/15/2005
CONTRACTOR: ELMO GREER & SONS, LLC
BID PRICE : $18,128,912.55
EST. COMPLETION DATE: SEPTEMBER, 2009